Production schedule by group
above: Our first Vestaboard made and assembled by our partner factory today on December 19, 2019
We are ramping up production to begin delivery of the high quality, gorgeous Vestaboard we have promised. If you’re in San Francisco, stop by our office to see Vestaboard in person!
Even though we are not on a timely schedule for our estimated Fall 2019 launch, we would very much like for you to celebrate the recent milestone with us of having completed our first Vestaboard with production parts, which we assembled in our studio in San Francisco. It looks and sounds incredible!
Even more exciting, our partner factory and team members will complete building the first 15 production Vestaboards (EVT) in the coming days. I have been on site at our partner factory near Shenzhen, China overseeing this phase, along with Ian Guyer, our operations lead who moved to the area earlier this year, along with Dominic Monette, our firmware engineer and Adam Reed-Erickson, a critical mechanical engineering lead.
I took this photo today of the first ever fully assembled Vestaboard by our partner factory, with our team observing the process. Coincidentally today the US patent office approved issuance of a second patent to Vestaboard. It was an exciting day!
It took us 12 months from January 2018 to build our first prototype Vestaboard (after over two years of prototyping the character unit or "Bit"), 10 months from our first prototype to a Vestaboard that was fully designed for manufacturing, and now less than 2 months to see our first unit fully assembled by our partner factory. You can learn more about production and see video in our post Insight into Production.
It will take us just a few days to manufacture the first 15 Vestaboards. We will then test these units rigorously for several weeks, realize safety approvals and build a small batch of 50 shippable units next. We expect to begin production in full of 500 units per month in April.
Thank you in advance for your patience as you review the table below to see which production month aligns with your Shipping Group. To find your Shipping Group, see the Orders tab in the portal, click ‘details’, then scroll down. If you have questions, chat or email us at support@vestaboard.com.
Production Schedule by Shipping Group
|
15 EVT Units |
December 16-21 |
|
|
Safety approvals and reliability testing |
January 2020 |
|
|
50 DVT Units, and observation |
First 50 |
February/March 2020 |
|
Production Month 1 - 500 Units |
Shipping Group 1 |
April/May 2020 |
|
Production Month 2 - 500 Units |
Shipping Groups 2 and 3 |
May/June 2020 |
|
Production Month 3 - 500 Units |
Shipping Groups 4 and 5 |
June/July 2020 |
|
Production Month 4 - 500 Units |
Shipping Groups 6 and 7 |
July/Aug 2020 |
|
Production Month 5 - 500 Units |
Shipping Groups 8, 9 & 10 |
August/Sep 2020 |